New Delhi, Nov 26 (PTI) Infrastructure projects worth more than Rs 150 crore each recorded a cumulative cost overrun of approximately Rs 3,28,452 crore, according to a monthly government report for October 2026.

     About 1,862 ongoing infrastructure projects across 17 central ministries and departments were monitored, and it was found that the total revised cost was Rs 38,11,292 crore compared to the original cost of Rs 34,82,840 crore.

     However, the report did not specify the actual number of projects that faced cost overrun.

     The cumulative expenditure incurred on these projects stands at Rs 17.87 lakh crore, accounting for approximately 46.88 per cent of the project cost, indicating steady progress in project implementation, the Ministry of Statistics and Programme Implementation (MoSPI) said in its monthly report for October on Wednesday.

     A significant proportion of projects are at advanced stages, with 649 projects (35 per cent achieving over 80 per cent physical progress, while 326 (18 per cent) have crossed 80 per cent financial completion.

     The data also reflects a balanced pipeline, with projects distributed across early and advanced stages of implementation.

     Out of 1,862 ongoing infrastructure projects, there are 790 Mega projects (project cost of Rs 1,000 crore & above), and 1,072 Major projects (below Rs 1,000 crore).

     The Transport & Logistics sector accounts for the highest number of ongoing projects (1,324), with a cumulative cost of Rs 20.37 lakh crore, underscoring the priority given to connectivity-driven infrastructure growth.

     The report said that the physical and financial progress broadly move in tandem, with a large number of projects clustered at the initial (0–20 per cent) and advanced (81–100 per cent) stages, indicating a pipeline of newly started projects alongside many nearing completion.

     While physical progress exceeds financial advancement in the 81–100 per cent range, financial progress is relatively higher in the early stages, reflecting upfront expenditure patterns in project implementation.

     Ministry of Road Transport & Highways accounts for the highest number of projects at 972 (52 per cent of total 1,862 projects), and a share of total revised project cost of Rs 9.55 lakh crore (25 per cent of total project cost Rs 38.11 lakh crore), highlighting its central role in national infrastructure development.

     The Ministry of Railways has 288 ongoing projects (15 per cent), with a total revised project cost of Rs 7.38 lakh crore (19 per cent).

     The Coal Ministry accounts for 121 ongoing projects (7 per cent), with a total revised project cost of Rs 2.22 lakh crore (6 per cent).

     The Ministry of Petroleum & Natural Gas, Ministry of Power, Ministry of Housing & Urban Affairs, and the Department of Water Resources, River Development & GR are implementing 117, 108, 50, and 33 projects, with associated project costs of Rs 4.42 lakh crore, Rs 6.55 lakh crore, Rs 3.44 lakh crore, and Rs 1.93 lakh crore, respectively.

     The remaining 173 projects (9 per cent), with a total project cost of Rs 2.63 lakh crore (7 per cent), are distributed across various Ministries and Departments, including Higher Education, Civil Aviation, Steel, Telecommunications, Labour & Employment, Ports, Shipping & Waterways, Health & Family Welfare, Mines, DPIIT and Sports.

(This story has not been edited by THE WEEK and is auto-generated from PTI)
Disclaimer: Comments posted here are the sole responsibility of the user and do not reflect the views of THE WEEK. Obscene or offensive remarks against any person, religion, community or nation are punishable under IT rules and may invite legal action.