New Delhi, Nov 26 (PTI) The Ministry of Road Transport and Highways (MoRTH) on Thursday proposed a comprehensive revision of

New Delhi, Nov 26 (PTI) The Ministry of Road Transport and Highways (MoRTH) on Thursday proposed a comprehensive revision of

New Delhi, Nov 26 (PTI) The Ministry of Road Transport and Highways (MoRTH) on Thursday proposed a comprehensive revision of

New Delhi, Nov 26 (PTI) The Ministry of Road Transport and Highways (MoRTH) on Thursday proposed a comprehensive revision of the Model Request for Proposal (RFP) for Engineering, Procurement and Construction (EPC) contracts, to strengthen quality and accountability in highway project execution.

     The proposed revision updates the existing framework issued in March 2019, and seeks to encourage performance-oriented contractors, strengthen quality and accountability in highway project execution, and make the EPC bidding process more transparent and robust, MoRTH said in a statement.

     The statement said the proposed revisions aim to strengthen bidder eligibility, improve assessment of financial and technical capacity, promote accountability and ensure greater transparency in the bidding and contract award process.

     According to the ministry, the proposed revision covers changes across six RFP sections, 12 appendices and nine annexures to Appendix-IA, besides introducing three entirely new formats.

     As per the proposed revision, MoRTH said a contractor's highway bid capacity will now depend on their performance rating and execution delays in ongoing projects, replacing the earlier approach based on the best-performing financial year.

     The ministry said in a statement that new disclosure requirements cover ongoing disputes, litigation, arbitration and penal actions, with bidders required to keep the information updated during the bidding process.

     According to the ministry, existing project commitments will be weighted according to execution delays, while contractor performance ratings will directly influence the bidder's eligible capacity.

     Moreover, the ministry said the provision for sequential counter-offers to the second and third lowest bidders has been removed. "Where the lowest bidder is found ineligible, the Authority may annul the process and invite fresh bids," it said.

     The ministry said the maximum number of joint venture (JV) members has been reduced from three to two. Joint ventures will generally be permitted for projects above Rs 1,000 crore, with enhanced minimum participation requirements for the other member, it added.

     "Performance Security has been linked to contractor ratings, ranging from 3 per cent to 5 per cent of the bid price," it said, adding the proposed framework also provides for electronic submission of security instruments.

     The ministry said the number of identified non-performance criteria has been rationalised from 20 to 7, with clearly defined thresholds and look-back periods.

     Provisions relating to catastrophic failures, project termination, debarment and insolvency have also been strengthened, it added.

(This story has not been edited by THE WEEK and is auto-generated from PTI)