WBPDCL expects to complete construction of Rs 4 400cr Sagardighi power plant in 42 months

    Kolkata, Jul 12 (PTI) State-run West Bengal Power
Development Corporation Ltd (WBPDCL) has started preliminary
works for setting up its Rs 4,400 crore Sagardighi super-
critical plant from this month and expects to complete the
construction of the unit over the next three-and-half years,
an official said on Sunday.
    The company has decided to consider July 1 as the
"zero date" for the implementation of the 660-MW thermal power
plant project in Murshidabad district, he said.
    "Preliminary works like ground-levelling have
commenced. July 1 is the zero date for the Sagardighi super-
critical power plant project.
    "It will take 42 months to complete the construction
of the unit and another three months will be required for
synchronisation before the commission of it," WBPDCL director
Indranil Dutta told PTI.
    Usually, the project completion period is counted from
the zero date.
    The total project cost was estimated at Rs 4,400
crore, he said.
    "The financial closure has been achieved and the Power
Finance Corporation is offering the debt," he said.
    Bharat Heavy Electricals Ltd (BHEL) has bagged an
order worth Rs 3,500 crore for supplying boiler, turbine,
generator (BTG) for the project, he said.
    The WBPDCL has four units of 1600-MW in Sagardighi and
the fifth one will increase the plant's capacity to 2,260 MW.
    The power producer has four more plants in Bandel,
Bakreswar, Kolaghat and Santaldihi and an overall generation
capacity of 3,150 MW. PTI BSM